Continued roof work & Framing of the offices on the 2nd floor.
Friday, September 25, 2009
September Progress Part I
Things have been moving along quickly throughout the month of September.
At the beginning of the month, a gigantic steel structure towers over the construction site ready for the next phase.

At the beginning of the month, a gigantic steel structure towers over the construction site ready for the next phase.
During the first week, a truck was brought in to pump the concrete flooring for the 3rd story. The roofing for the back side of the building also started going up.
After the Labor Day holiday weekend, a smaller concrete pumping truck was brought in to pour the second story floor. This second week of September also saw progress on the roof on the front side of the building.