Wednesday, December 2, 2009

End of Year Progress

It has been awhile since our last post. The holidays have come and gone but work continues on the new buliding. The geothermal well drilling has been completed, and the system has been setup.


Skylights have been installed in the roof to reduce the amount of electricity needed upstairs.

The front entrance peak was installed in November.


The roof has been finished, complete with the shingles. Framing for the first floor has started, and the sheetrock walls are up on the second floor. The windows are currently being installed on the back side of the buliding.


Progress is moving along as we look towards a springtime move in date.