Sometimes, we don’t realize how much progress we’re making on the building because we see it every day. But if you take a look at these photos, you’ll see for yourself how fast the steel framework is going up.
We took these photos on four successive Thursdays: July 31, Aug. 6, Aug. 13 and Aug. 20. And we’re right on schedule to finish the framework by mid-September.
With all the rain and thunderstorms we’ve had this summer, we have to take our hats off to our construction crews – Fast Trek Steel of Coxsackie is erecting the steel -- for keeping us on track.
After that, a bunch of things start happening all at once. We no sooner finish the framework when we start pouring concrete for the floors – third floor, then second a few days later.
At the same time, we’ll begin work on the roof, insulation and the underslab plumbing.
And by fall, we’ll begin work on the fire-protection systems.
Pretty busy, indeed. We’re excited by it.